Trotter Road Work Begins Soon

From HoCo gov:

A Howard County construction project to extend public water and sewer to the Trotter Crossing Development, in the vicinity of Southwind Circle in Clarksville, is scheduled to begin on or about Monday, May 4. The project will include construction of approximately 1,200 linear feet of both 8-inch water main and 8-inch sewer main, just north of the Trotter Road traffic circle. Weather permitting the project should be completed by mid-June.

During the project, Trotter Road thru traffic will be detoured using Maryland Route 108 and Great Star Drive. Flagging operations will be in place to direct traffic as needed, and signs will be posted to advise motorists of the construction and detour. In addition, a recorded message at 410-313-3637 will carry project details and updates about the project.

1 comment:

Anonymous said...

It is now July 1 and Trotter Rd. is still closed. There is no updated message from the county on the 410-313-3637 recording regarding when the work will be finished.